S. N. | Work Details | Location | Start Date | End Date | Status | Remarks |
1 | Fire Pipe Paint Works | All Tower | 01/07/23 | 20/08/23 | Closed | All tower fire pipes (Vertical & Horizontal) paint work done. Upper & Lower Basement Fire Ring Line Paint work is balance |
2 | Fire Vertical Pipes, Landing valve, Butterfly, Hosereel Drum Repair work | All Tower | 01/07/23 | 20/08/23 | Closed | All tower repair work done |
3 | Pump Room Paint work | A2 tower lower basement | 01/07/23 | Closed | Pump room pipes paint work done | |
4 | Replacement of mechanical seal in Flushing Pump # 1 | A2 tower lower basement | 13/07/23 | 13/07/23 | Closed | New mechanical seal replaced |
5 | DG Set shed work | A8 tower ground floor | 14/07/23 | Closed | DG Set shed work done | |
6 | New submersible pump | Back side of common washroom near main gate | 15/07/23 | 15/07/23 | Closed | New pump purchased and fixed in Rain water harvesting pit |
7 | Security Guard room | Main entry gate | 17/07/23 | 20/07/23 | Closed | New Almira / drawer prepared for security room at the main gate |
8 | A5 tower terrace water overflow issue | A5 tower terrace | 21/07/23 | 22/07/23 | Closed | Plumbing pipe connected to overflow outlet of water tanks linked directly to drain mechanism of plumbing shaft |
9 | Club R.O. | Club near swimming pool | 23/07/23 | 23/07/23 | Closed | Fixing of pressure release valve to control the water pressure for R.O. machine |
10 | Park renovation | In front of A1 tower (Outside the exit gate) | 24/07/23 | 28/07/23 | Closed | Outside park renovated by doing followings 1) Pole fixed to cover the area 2) Area covered by fencing wire to avoid entry of outside cows 3) New grass & new plants planted |
11 | GYM machine repair & add of new parts | GYM | 25/07/23 | 25/07/23 | Closed | Existing machines repaired and some new machine introduced |
12 | CCTV work | Security guard room at the main gate | 27/07/23 | 01/08/23 | Closed | Centralised Display installaed at main gate security room for access of CCTV Coverage |
13 | Biometric Machine | Security guard room at the main gate | 27/07/23 | 30/07/23 | Closed | Existing biometric machine shifted from Club library to the main gate |
14 | Stone ghisai work | A9 tower lower basement lift lobby area | 28/07/23 | 02/08/23 | Closed | Stone ghisai work done as it was pending since SBPL time |
15 | Swimming pool plant room stainer work | Swimming pool plant room | 28/07/23 | 31/07/23 | Closed | New ‘T’ stainer installed |
16 | Yoga park floor repair work | Yoga Park near A4 tower ground floor | 29/07/23 | 01/08/23 | Closed | Yoga park floor repair work done |